Jinan Siji CNC Machine Tool Co., Ltd. Environmental Impact Assessment of New CNC Machine Tool Production Projects
1. Name and summary of the construction project
Project Name: Jinan Siji CNC Machine Tool Co., Ltd. New CNC Machine Tool Production Project
Summary: Jinan Siji CNC Machine Tool Co., Ltd. plans to locate the existing projects of two existing factories in Yingxiu Road and Hualong Road, High-tech Zone, Licheng District Relocated to Sun Village, Jinan High-tech Development Zone, which is about 30 kilometers east of the urban area, and optimized and adjusted on the basis of the existing production process and process equipment to increase the intelligence and reliability of products and further increase the production scale , improve the competitiveness of enterprises themselves.
The company's newly relocated factory site is located in the north of Sun Village, Jinan High-tech Industrial Development Zone. The factory area is adjacent to No. 35 Road in the north, Jinan Geely Company in the south, Shandong Linwo Heavy Truck Co., Ltd. in the west, and Chunhui Road in the east. The total investment of the proposed project is 540 million yuan. The plant covers an area of 15.04hm2 (including 1.7hm2 of municipal planning and construction land), with a total construction area of 112,800 m2. It will be constructed in two phases. The designed production scale is 2990 CNC machine tools per year. The labor force of the proposed project is 800 people. There are 270 working days throughout the year, 8 hours a day.
Second, the name and contact information of the construction unit of the construction project
Constructor: Jinan Siji CNC Machine Tool Co., Ltd.
Contact: Cui Keyuan
Telephone:13256766899
Mail Mail:2584980869@qq.com
Three, the name and contact information of the organization undertaking the environmental impact assessment work
Evaluation agency: Jinan Environmental Protection Planning and Design Institute
Contact: Fan Linxiang
Telephone: 82050737
Mail Mail:fanlinxiang@jn.gov.com
IV. Environmental impact assessment work procedures and main work content
Working procedures: After receiving the EIA entrustment letter, the evaluation unit will find out the pollution discharge link of the construction project and determine the generation of pollutants through the investigation, monitoring and engineering analysis of the current situation of the environment in the area where the project is located. According to the pollution prevention measures and technologies adopted by the project, predict the impact scope and degree of the proposed project on the surrounding environment during and after completion, and demonstrate the feasibility of the project construction from the perspective of environmental protection. And according to the public opinions and suggestions reflected by the public participation, it proposes measures and countermeasures that the construction unit should take to prevent pollution and improve the quality of the environment, and provide a scientific basis for decision-making departments.
Main work content: engineering analysis, regional environmental status investigation, environmental air impact assessment, surface water environmental impact analysis, groundwater environmental impact assessment, acoustic environmental impact assessment, solid waste environmental impact analysis, Environmental impact analysis during construction period, environmental risk assessment, environmental economic profit and loss analysis, site selection rationality analysis, environmental protection measures and their economic and technical demonstration, total control analysis, environmental management and monitoring plan, environmental impact assessment conclusion.
V. Main issues for soliciting public opinions
① Current local economic development; ② Main problems of current local economic development;
③ Current local major environmental issues; ④ Feasibility of environmental protection measures to be taken in the proposed project;
⑤ What is your attitude towards the construction of this project; ⑥ Opinions and suggestions on the construction of this project.
6. The main ways for the public to put forward their opinions
(1) Within ten days from the date of the announcement, the construction unit or the entrusted environmental impact report preparation unit will provide the public with inquiries and consultation services for relevant information.
(2) If the public has environmental protection opinions on the construction project, within ten days from the date of this announcement, they may report to the construction unit (Jinan Fourth Machinery) by telephone, letter or E-mail CNC Machine Tool Co., Ltd.) or the preparation unit of the environmental impact report (Jinan Environmental Protection Planning and Design Institute) to express their opinions, or send their opinions in written text to the local environmental protection authority.
Announcement release unit: Jinan Siji CNC Machine Tool Co., Ltd.
Published: September 12, 2012